A project is nearing completion. The contingency time has been consumed. To ensure that the final deliverables are achieved within budget, the project manager has asked the team to follow a rigorous process. This Is causing some resistance among the team members.What should the project manager do to address the growing resistance?
选项:
A: Crash the project schedule and ask project team members to work overtime to meet the new timeline.
B: Motivate project team members by offering incentives to complete the project on time.
C: Describe to the team members how specific tools and techniques can be used to finish on time.
D: Convince team members to use a specific methodology to complete the project on time.