.A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.How should the project manager handle this situation?
选项:

A: Request to meet with the team member and ask that any issues be escalated separately.
B: Reprimand the team member and provide immediate coaching on goal alignment.
C: Proceed with defining the goals with the team members given the majority approval from the team.
D: Approach the team member with empathy and obtain agreement through collaboration.