A project manager has just been assigned to a team that is developing a new design product。The work breakdown structure (VW/BS) has been created and the activities have beenassigned to the team members。The project manager finds that there are activities that could be completed sooner by otherteam members。 If the current assignments are left as is, the project could be delayed 2weeks。What should the project manager do in this situation?
选项:

A: Review the work allocation and reassign some tasks to shorten the critical path。
B: Maintain the task assignments as planned and compress the other tasks to keep theproject on schedule。
C: Ask the team members to work overtime to finish the tasks on time according to theschedule。
D: Keep the task assignments unchanged since the project management plan has beenapproved。

发布时间:2024-05-16 21:09:23
推荐参考答案 ( 由 搜题小帮手 官方老师解答 )
联系客服
答案:

以下文字与答案无关

提示:有些试题内容 显示不完整,文字错误 或者 答案显示错误等问题,这是由于我们在扫描录入过程中 机器识别错误导致,人工逐条矫正总有遗漏,所以恳请 广大网友理解。

相关试题
登录 - 搜题小帮手
点我刷新
立即注册
注册 - 搜题小帮手
点我刷新
立即登录