You have been assigned to lead an agile project. However, when you meet with your team for the first time, you realize that due to various company's imposed constraints, most of the team members would not be able to be 100% dedicated to the project. What is your best course of action?
选项:
A:Switch the development approach from agile to scrum
B:Increase iteration length from two to four weeks
C:Offer rewards to the team members to work overtime
D:Adjust assignments based on individual capacity