【单选】Portfolio manager proposes a new program that is expected to be initiated.The program business case shows that the new program meets the portfolio ROl and NPV targets. What is the next document the program manager should develop?
选项:
A:Program work breakdown structure (PWBS)
B:Program charter.
C: Program management plan.
D:Benefits management plan