单选] A program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced. The program manager will use the qualified seller list to do which of the following ?
选项:
A:Plan a proposal evaluation system
B:Prepare the program procurement management plan.
C:Perform the required program budget updates.
D:Issue requests for proposals.