In agile projects, overall planning is at a high level, and only the near-term work is planned in detail. The project work is conducted in iterations (sprints) that are normally:
选项:
A: no more than one calendar year
B: a variable length depending on project scope
C: a fixed length of two or four weeks
D: assigned to one person on the team