NO.43 A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system. Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
选项:

A:Infinite resource and infinite strategy
B:Finite resource and finite strategy
C:Finite resource and infinite strategy
D:Infinite resource and finite strategy

发布时间:2024-06-25 20:08:30
推荐参考答案 ( 由 搜题小帮手 官方老师解答 )
联系客服
答案: