Your project has several risks that may cause serious financial impact if they occur. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They'd like you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?
选项:

A:Risk response plan
B:Contingency reserve
C:Risk response
D:Quantitative analysis

发布时间:2024-03-28 09:30:45
推荐参考答案 ( 由 搜题小帮手 官方老师解答 )
联系客服
答案: