933For an auditor, it is very important to understand the different forms of project organization and their implication in the control of project management activities. In which of the following project organization form is management authority shared between the project manager and the department head?
选项:

A:Influence project organization
B:Pure project organization
C:Matrix project organization
D:Forward project organization