What should a Development Team do if it realizes it has selected too much work after starting the Sprint?
选项:
A:Modify the definition of "Done" to ensure all Product Backlog items can be done by the end of the Sprint.
B:Work with the Product Owner to remove some work or Product Backlog items as soon as possible
C:Add additional team members to handle the extra work
D:Continue working and update the Product Owner at the Sprint Review.