Which of the following is the BEST indication that a software development project is on track to meet ts completion deadline?
选项:
A:The planned software go-live date has been communicated in advance to end users and stakeholders.
B:Project plan due dates have been documented for each phase of the software development life cycle.
C:Technical specifications and development requirements have been agreed upon and formally recorded.
D:Issues identified during user acceptance testing (UAT) have been addressed prior to the original implementation date.